Closure of the Bureya River in April 2016 and Filling of the Plinth of the Lower Bureya Dam
- Авторлар: Il’inskaya A.I.1, Bobkov A.V.1, Gara V.S.1, Pareshnev A.S.1, Petrov V.V.1
-
Мекемелер:
- JSC Lenhydroproject
- Шығарылым: Том 51, № 3 (2017)
- Беттер: 274-280
- Бөлім: Article
- URL: https://journals.rcsi.science/1570-145X/article/view/245777
- DOI: https://doi.org/10.1007/s10749-017-0824-x
- ID: 245777
Дәйексөз келтіру
Аннотация
At the preliminary design stage, the closure of the Bureya river was scheduled for October 20, 2015. The actual status of construction necessitated rescheduling the river closure for March 20, 2016, alteration of design discharges, 3D simulation, and adjustment of design solutions. The actual conditions of river closure on April 19, 2016 are described.
Авторлар туралы
A. Il’inskaya
JSC Lenhydroproject
Хат алмасуға жауапты Автор.
Email: office@lhp.ru
Ресей, St. Petersburg
A. Bobkov
JSC Lenhydroproject
Email: office@lhp.ru
Ресей, St. Petersburg
V. Gara
JSC Lenhydroproject
Email: office@lhp.ru
Ресей, St. Petersburg
A. Pareshnev
JSC Lenhydroproject
Email: office@lhp.ru
Ресей, St. Petersburg
V. Petrov
JSC Lenhydroproject
Email: office@lhp.ru
Ресей, St. Petersburg
Қосымша файлдар