Closure of the Bureya River in April 2016 and Filling of the Plinth of the Lower Bureya Dam
- 作者: Il’inskaya A.1, Bobkov A.1, Gara V.1, Pareshnev A.1, Petrov V.1
-
隶属关系:
- JSC Lenhydroproject
- 期: 卷 51, 编号 3 (2017)
- 页面: 274-280
- 栏目: Article
- URL: https://journals.rcsi.science/1570-145X/article/view/245777
- DOI: https://doi.org/10.1007/s10749-017-0824-x
- ID: 245777
如何引用文章
详细
At the preliminary design stage, the closure of the Bureya river was scheduled for October 20, 2015. The actual status of construction necessitated rescheduling the river closure for March 20, 2016, alteration of design discharges, 3D simulation, and adjustment of design solutions. The actual conditions of river closure on April 19, 2016 are described.
作者简介
A. Il’inskaya
JSC Lenhydroproject
编辑信件的主要联系方式.
Email: office@lhp.ru
俄罗斯联邦, St. Petersburg
A. Bobkov
JSC Lenhydroproject
Email: office@lhp.ru
俄罗斯联邦, St. Petersburg
V. Gara
JSC Lenhydroproject
Email: office@lhp.ru
俄罗斯联邦, St. Petersburg
A. Pareshnev
JSC Lenhydroproject
Email: office@lhp.ru
俄罗斯联邦, St. Petersburg
V. Petrov
JSC Lenhydroproject
Email: office@lhp.ru
俄罗斯联邦, St. Petersburg