Closure of the Bureya River in April 2016 and Filling of the Plinth of the Lower Bureya Dam


Citar

Texto integral

Acesso aberto Acesso aberto
Acesso é fechado Acesso está concedido
Acesso é fechado Somente assinantes

Resumo

At the preliminary design stage, the closure of the Bureya river was scheduled for October 20, 2015. The actual status of construction necessitated rescheduling the river closure for March 20, 2016, alteration of design discharges, 3D simulation, and adjustment of design solutions. The actual conditions of river closure on April 19, 2016 are described.

Sobre autores

A. Il’inskaya

JSC Lenhydroproject

Autor responsável pela correspondência
Email: office@lhp.ru
Rússia, St. Petersburg

A. Bobkov

JSC Lenhydroproject

Email: office@lhp.ru
Rússia, St. Petersburg

V. Gara

JSC Lenhydroproject

Email: office@lhp.ru
Rússia, St. Petersburg

A. Pareshnev

JSC Lenhydroproject

Email: office@lhp.ru
Rússia, St. Petersburg

V. Petrov

JSC Lenhydroproject

Email: office@lhp.ru
Rússia, St. Petersburg


Declaração de direitos autorais © Springer Science+Business Media, LLC, 2017

Este site utiliza cookies

Ao continuar usando nosso site, você concorda com o procedimento de cookies que mantêm o site funcionando normalmente.

Informação sobre cookies