Optimization of Start-Up of a Fully Fired Combined-Cycle Plant with GT13E2 Gas Turbine


Дәйексөз келтіру

Толық мәтін

Ашық рұқсат Ашық рұқсат
Рұқсат жабық Рұқсат берілді
Рұқсат жабық Тек жазылушылар үшін

Аннотация

The principles of starting up the steam power unit of the Hrazdan-5 fully fired combined-cycle power unit (Hrazdan, Armenia) are considered. This plant has neither a bypass stack for gas discharge from the gas turbine nor an external steam source for the steam-turbine gland and prestarting deaeration. Emphasis is placed on the differences between the start-up procedure followed at the plant and the procedure provided by the RD 34.25.512 Standard Instructions on Startup from Various Thermal States and Shutdown of 300-MW Boiler-Turbine Sets with K-300-240 LMZ Turbine.

Авторлар туралы

A. Anisimov

LvivORGRES

Хат алмасуға жауапты Автор.
Email: anisimov.o@email.ua
Украина, Lviv

M. Klub

LvivORGRES

Email: anisimov.o@email.ua
Украина, Lviv

K. Sargsyan

“Hrazdan-5” of JSC “Gazprom Armenia,”

Email: anisimov.o@email.ua
Армения, Hrazdan

S. Eritsyan

“Hrazdan-5” of JSC “Gazprom Armenia,”

Email: anisimov.o@email.ua
Армения, Hrazdan

G. Petrosyan

“Hrazdan-5” of JSC “Gazprom Armenia,”

Email: anisimov.o@email.ua
Армения, Hrazdan

A. Avtandilyan

“Hrazdan-5” of JSC “Gazprom Armenia,”

Email: anisimov.o@email.ua
Армения, Hrazdan

A. Gevorgyan

“Hrazdan-5” of JSC “Gazprom Armenia,”

Email: anisimov.o@email.ua
Армения, Hrazdan


© Springer Science+Business Media New York, 2016