Optimization of Group Incentive Schemes

Capa

Citar

Texto integral

Acesso aberto Acesso aberto
Acesso é fechado Acesso está concedido
Acesso é fechado Somente assinantes

Resumo

This paper considers the problem of motivating the reduction of project duration. The duration cuts of project works and the corresponding costs are given. A group incentive scheme is used to compensate for the costs. In this scheme, all works are partitioned into groups and a unified incentive scheme is applied for each group. Two types of unified incentive schemes are studied for groups, namely, linear and jump ones. The problem is to partition all project
works into groups and choose an appropriate incentive scheme for each group by minimizing the total incentive fund. Solution algorithms are proposed based on determining the shortest
path in the network. Special cases are also analyzed (partition with the minimum number of groups and partition with the maximum number of groups).

Sobre autores

V. Burkov

Trapeznikov Institute of Control Sciences, Russian Academy of Sciences

Email: vlab17@bk.ru
Moscow, Russia

I. Burkova

Trapeznikov Institute of Control Sciences, Russian Academy of Sciences

Email: irbur27@gmail.com
Moscow, Russia

A. Kashenkov

Vologda State Technical University

Autor responsável pela correspondência
Email: alex27k@mail.ru
Vologda, Russia

Bibliografia

  1. Новиков Д.А. Стимулирование в организационных системах. М.: Синтег, 2003.
  2. Новиков Д.А., Цветков А.В. Механизмы стимулирования в многоэлементных организационных системах. М.: Апостроф. 2000.
  3. Бурков В.Н., Буркова И.В. и др. Механизмы управления: Мультифункциональное учебное пособие / Под ред. Д.А. Новикова. Изд. 2-е переработанное и доп. М.: ЛЕНАНД, 2013.

Declaração de direitos autorais © The Russian Academy of Sciences, 2023

Este site utiliza cookies

Ao continuar usando nosso site, você concorda com o procedimento de cookies que mantêm o site funcionando normalmente.

Informação sobre cookies