Using lean manufacturing tools in materials supply management during the life cycle of a construction project
- Authors: Oparina L.A.1, Barzygin E.A.1, Gridneva Y.A.1, Kasyanenko N.S.1
-
Affiliations:
- Ivanovo State Polytechnic University (IVSPU)
- Issue: Vol 19, No 5 (2024)
- Pages: 826-835
- Section: Technology and organization of construction. Economics and management in construction
- URL: https://journals.rcsi.science/1997-0935/article/view/259916
- ID: 259916
Cite item
Full Text
Abstract
About the authors
L. A. Oparina
Ivanovo State Polytechnic University (IVSPU)
Email: L.A.Oparina@gmail.com
ORCID iD: 0000-0001-5534-727X
E. A. Barzygin
Ivanovo State Polytechnic University (IVSPU)
Email: barzygin@mail.ru
Ya. A. Gridneva
Ivanovo State Polytechnic University (IVSPU)
Email: yaroslava.l.a1@gmail.com
ORCID iD: 0000-0003-1570-7087
SPIN-code: 8504-1658
N. S. Kasyanenko
Ivanovo State Polytechnic University (IVSPU)
Email: kasiyanenko@gmail.com
ORCID iD: 0000-0002-4046-9300
References
- Кудреватых В.В. Особенности управления требованиями в сфере управления проектами в инжиниринговой компании полного цикла // Вестник МГСУ. 2020. Т. 15. № 8. С. 1175–1190. doi: 10.22227/1997-0935.2020.8.1175-1190
- Лапидус А.А., Чапидзе О.Д. Совершенствование анализа факторов технических рисков с использованием комплексной модели FLDS на примере строительства многоэтажных жилых зданий // Вестник МГСУ. 2021. Т. 16. Вып. 12. С. 1608–1619. doi: 10.22227/1997-0935.2021.12.1608-1619
- Wang Y., Chen X. Risk management for construction material supply chain : a review // Journal of Construction Engineering and Management Eng. 2020.
- Щербанин Ю.А., Шиков В.О. Рисковые события и их характеристики // Научные труды: Институт народнохозяйственного прогнозирования РАН. 2019. Т. 17. С. 54–74. doi: 10.29003/m811.sp_ief_ras2019/54-74
- Оно Т. Производственная система Тойоты. Уходя от массового производства. М. : Институт комплексных стратегических исследований, 2008. С. 121–125.
- Hammad Al-Nasseri, Kristian Widén, Radhlinah Aulin. A taxonomy of planning and scheduling methods to support their more efficient use in construction project management // Journal of Engineering Design and Technology. 2016. Vol. 14. Issue 1. Pp. 580–601. doi: 10.1108/JEDT-11-2013-0078
- Поляков А.Н. Американские технократы. Генри Лоуренс Гантт // Management: журнал. 2021. № 1 (57). С. 58–63.
- Morris P.W.G., Pinto J.H. The Gantt chart: A century of evolution // Project Management Journal Eng. 2019.
- Practice Standard for Work Breakdown Structure. 3rd ed. Project Management Institute Eng. Newtown Square, PA. USA. 2019.
- Zein M.A., Al-Salman A.M. A review of hierarchical structures in project management // International Journal of Project Management Eng. 2021.
- Supriyono, Nur Chasanah. Software development project management based on work breakdown structure and ODOO ERP // Jurnal Teknik Informatika (JUTIF). 2023. Vol. 4. Issue 4. Pp. 893–898. doi: 10.52436/1.jutif.2023.4.4.1077.
- Srivastava R.K., Jain S.K. A multi-level approach to project planning and control // International Journal of Project Management Eng. 2020.
- Ali J.H., Al-Suliman S.A. A comparative study of network scheduling techniques for construction projects // Journal of Construction Engineering and Management, 2021.
- Ryan G. Even more schedule for sale. Advanced work packaging for construction projects. AuthorHouse Eng. Bloomington, Indiana USA. 2017. P. 135.
- Al-Hussein M.R., Odeh M.T. Advanced work packaging: An innovative approach to construction planning and execution // Journal of Construction Engineering and Management Eng. 2017.
- Bradley Copeland. Digital advanced work packaging — a case study in construction-led delivery // The APPEA Journal. 2023. Vol. 63. Issue 2. Pp. S169-S172. doi: 10.1071/AJ22046.
- Кулаков К.Ю., Орлов А.К., Канхва В.С. Цепочки создания ценности в строительстве на основе концепции бережливого производства в условиях цифровой трансформации // Вестник МГСУ. 2023. Т. 18. Вып. 10. С. 1647–1660. doi: 10.22227/1997-0935.2023.10.1647-1660
- Zhang X., Azhar S., Nadeem A., Khalfan M. Using Building Information Modelling to achieve Lean principles by improving efficiency of work teams // International Journal of Construction Management. 2018. Vol. 18. Issue 4. Pp. 293–300. doi: 10.1080/15623599.2017.1382083
- Porter M.E., Heppelmann J.E. How smart, connected products are transforming competition // Harvard Business Review. November 2014. URL: https://hbr.org/2014/11/how-smart-connected-products-are-transforming-competition
Supplementary files