Limitations on the Rate of Impoundment and Drawdown of a Concrete Dam Reservoir (Example of the Arch-Gravity Dam of the Sayano-Shushenskaya HPP)
- 作者: Vul’fovich N.A.1, Potekhin L.P.1
-
隶属关系:
- JSC Lengidroproekt
- 期: 卷 52, 编号 1 (2018)
- 页面: 39-46
- 栏目: Article
- URL: https://journals.rcsi.science/1570-145X/article/view/246070
- DOI: https://doi.org/10.1007/s10749-018-0907-3
- ID: 246070
如何引用文章
详细
Reasons are examined for the necessity of eliminating restrictions on the speed of impoundment (drawdown) of a reservoir, ensuring safe operation of the structure. The effect of the rate of change of the HWL on the rate of change of radial displacements of a dam is studied. It is shown that increasing the rate of reservoir impoundment does not worsen the stress-strain state of the structure.