Special Operations to Stabilize the Powerhouse of the Zagorsk PSPP-2
- Autores: Korolev V.1, Smirnov O.1, Argal É.1, Radzinskii A.1, Kim R.1, Aleksandrov A.2
-
Afiliações:
- Gidrospetsproekt, Ltd.
- Institute Hydroproject, Ltd.
- Edição: Volume 52, Nº 3 (2018)
- Páginas: 249-255
- Seção: Hydrotechnical Construction
- URL: https://journals.rcsi.science/1570-145X/article/view/246167
- DOI: https://doi.org/10.1007/s10749-018-0940-2
- ID: 246167
Citar
Resumo
A work package for filling the voids under the pumped-storage powerhouse and pressure grouting to strengthen the foundation soil is described. The compositions of the injectable grouts and specially designed composite material are presented. The results are analyzed.
Palavras-chave
Sobre autores
V. Korolev
Gidrospetsproekt, Ltd.
Autor responsável pela correspondência
Email: labkorolev@yandex.ru
Rússia, Moscow
O. Smirnov
Gidrospetsproekt, Ltd.
Email: labkorolev@yandex.ru
Rússia, Moscow
É. Argal
Gidrospetsproekt, Ltd.
Email: labkorolev@yandex.ru
Rússia, Moscow
A. Radzinskii
Gidrospetsproekt, Ltd.
Email: labkorolev@yandex.ru
Rússia, Moscow
R. Kim
Gidrospetsproekt, Ltd.
Email: labkorolev@yandex.ru
Rússia, Moscow
A. Aleksandrov
Institute Hydroproject, Ltd.
Email: labkorolev@yandex.ru
Rússia, Moscow