Behavior of the Concrete and Rock-Fill Dam at the Boguchanskaya HPP During the Period of Reservoir Filling (2012 – 2015)
- Autores: Volynchikov A.N.1, Gaziev É.G.2
-
Afiliações:
- JSC “Institut Gidroproekt,”
- Geodynamic Research Centre, an affiliate of JSC “Institut Gidroproekt,”
- Edição: Volume 50, Nº 1 (2016)
- Páginas: 23-32
- Seção: Article
- URL: https://journals.rcsi.science/1570-145X/article/view/245047
- DOI: https://doi.org/10.1007/s10749-016-0654-2
- ID: 245047
Citar
Resumo
Problems during filling of the reservoir under frozen rock bed conditions and rock-fill dam body are examined. Thawing of the dam bed and body resulted in an incline in the direction of the upper pool, which in turn caused local opening of the joint between the concrete dam and the asphalt-concrete water wall, which is the water-impermeable core of the dam.
Palavras-chave
Sobre autores
A. Volynchikov
JSC “Institut Gidroproekt,”
Autor responsável pela correspondência
Email: dpr-boges@hydroproject.ru
Rússia, Moscow
É. Gaziev
Geodynamic Research Centre, an affiliate of JSC “Institut Gidroproekt,”
Autor responsável pela correspondência
Email: erastgaziev@mail.ru
Rússia, Moscow
Arquivos suplementares