Local Erosion of the Channel After Reinforcement of the Millrace of the Votkinsk Hydroelectric Power Plant
- Authors: Veksler A.B.1, Fisenko V.F.2
-
Affiliations:
- JSC “VNIIG im. B. E. Vedeneeva”
- Votkinsk HPP, branch of JSC RusHydro
- Issue: Vol 51, No 1 (2017)
- Pages: 14-19
- Section: Article
- URL: https://journals.rcsi.science/1570-145X/article/view/245558
- DOI: https://doi.org/10.1007/s10749-017-0775-2
- ID: 245558
Cite item
Abstract
Changes during operation in the state of the segment where concrete reinforcement of the water channels of the Votkinsk hydroelectric plant join the Kama River are examined. The reasons for erosion during the 1990’s, including lowering of the water levels in the lower millrace, are examined. It is noted that after reinforcement of the hopper during 1998 – 2000, the state of this segment remains satisfactory and does not threaten the safety of the equipment.
About the authors
A. B. Veksler
JSC “VNIIG im. B. E. Vedeneeva”
Author for correspondence.
Email: VekslerAB@vniig.ru
Russian Federation, St. Petersburg
V. F. Fisenko
Votkinsk HPP, branch of JSC RusHydro
Email: VekslerAB@vniig.ru