On the Impact of Cleaning Widened Sections of Boreholes on the Bearing Capacity of Bored Situ-Cast Piles


如何引用文章

全文:

开放存取 开放存取
受限制的访问 ##reader.subscriptionAccessGranted##
受限制的访问 订阅存取

详细

A process aspect of installing bored situ-cast piles-the cleaning of widened borehole sections and its impact on the pile bearing capacity in slightly moist clay soil-is examined. Results are presented of field static tests on bored situ-cast piles fabricated using both the manufacturing process and installed in boreholes after they have been completely cleaned of drilling waste. A significant divergence is established between design and experimental values of soil resistance R under the pile, which suggests a need to update SP 24.1330.2011.

作者简介

A. Dzagov

N. M. Gersevanov Research Institute of Bases and Underground Structures

Email: smfe@mail.ru
俄罗斯联邦, Moscow

V. Kitaikin

N. M. Gersevanov Research Institute of Bases and Underground Structures

Email: smfe@mail.ru
俄罗斯联邦, Moscow

R. Chernov

N. M. Gersevanov Research Institute of Bases and Underground Structures

Email: smfe@mail.ru
俄罗斯联邦, Moscow

补充文件

附件文件
动作
1. JATS XML

版权所有 © Springer Science+Business Media New York, 2016